How long will a legacy migration take?
To work out how long a legacy migration will take, there is a process you can follow that will give an estimation with a good level of certainty. Like all process, there is some input, a process to follow, and then some output. This might seem basic, but it is important to think in this context.

This article is purposefully matter of fact and there is more of an explanation behind the process in the links below and explained more in the summary.
Input
- UI of the legacy system (Sandbox Site)
- Old documentation into the library (as much as possible)
- Database schema from the Legacy database schema
Process
The roots causes of legacy systems come from the loss of knowledge and control. To start rebuilding the knowledge and regaining momentum, record all your meetings!
- Create an extension identification spreadsheet from the External Resources
- Activity: Reverse Engineering Requirements into a backlog (initially record in the extension identification spreadsheet)
- Create a UX Flow (UI map, Menu flow, etc) from the UI of the legacy system
- Mark the UX Flow with the requirement ID’s from the backlog
- Cross check all requirements are covered in the UI and vica versa (super duper important for due diligence)
- Complete the extension identification spreadsheet
- Create an entity requirements spreadsheet from the External Resources
- Copy the tables name and backlog into the spreadsheet and identifiy what tables are needed for this milestone
- Copy the backlog into the plan on the platform and organise into boards
- Migrate the old schema (include only tables for this milestone) into the entity diagram
- Create as many of the pages and tiles into the UI diagram
- Fill out the secruity diagram and create any new entities with user extensions as required
- Create a time estimation spreadsheet from the external resources
- Complete any tech spikes to firm up estimations
- With at least 3 people, complete the estimations
Output
- Time Estimation Spreadsheet
- Extension Identification Spreadsheet
- Entity Requirements Spreadsheet
- UX Flow
- Plan with backlog
- Entity diagram
- UI diagram
- Security diagram
- Meeting Videos
- Tech Spike (if required)
Summary
If you are interested in getting qualified to answer the question: how long will a legacy migration take; I recommend joining up to Codebots and completing the Estimating a Project course in the academy. Some of the lessons cover:
- The Theory of Estimatin Software
- Software Development Methodologies
- Managing Risk
- Estimation Allowances
- Calculating the Estimation